Overview
America’s reliance on electricity has continued to grow.  Disruptions in electric service from weather events or natural disasters have tended to repeatedly prompt the seemingly logical next question “does it make sense to underground (UG) power lines to help minimize outages?”  Additionally, there has been a continuing trend for the removal of poles and overhead (OH) power lines to improve the aesthetics of a neighborhood or area.  While undergrounding power lines may seem on the surface to be a good way to go, the reality is that making the decision to put power lines underground is more complicated, and considerably more expensive.  Over the years, electric cooperatives and their regulating agencies or bodies have studied the undergrounding of power lines.  The large majority of these studies conclude that the cost of undergrounding is far more expensive than OH power systems.  New construction of UG facilities or conversion of existing OH power system facilities are both high cost alternatives for undergrounding.  These costs can also vary from location to location, but are considerably higher for UG than OH in all instances.  Besides the cost and aesthetics, factors regarding reliability need to be considered.  Overall, the question becomes “would the benefits achieved outweigh the costs incurred?”

The Edison Electric Institute (EEI) is the association of shareholder-owned electric companies that represent approximately 70 percent of the U.S. electric power industry.  They conducted a 2012 poll of electric customers to determine how willing they might be to pay for undergrounding.  The results of their poll showed the following:

The results indicated that 60 percent of electric customers were willing to pay at least 1−10 percent more on their power bills for undergrounding and another 11 percent of customers were willing to pay up to 20 percent more. However, fewer than 10 percent of the customers polled were willing to incur a bill increase of 100 percent to pay the more realistic cost for undergrounding. This information confirms the experience of most utilities and state commissions that the cost of undergrounding is a very important consideration and that customers have limited tolerance for higher costs for utility services to pay for undergrounding. (Hall, 2013, p. v)

The cost of undergrounding continues today to remain a challenge for electric cooperatives and their customers who want lines put underground.  If UG costs were the same as OH costs, the decision would be an easy one.  Despite the higher cost of UG, electric cooperatives do find value in building UG facilities in some instances.  For instance, new housing developments in the US are more and more being constructed with UG distribution power lines.  But, the construction of new UG transmission lines has been more varied and more rare as UG transmission lines are much more expensive. 

Hall (2013) also cites U.S. Energy Information Administration (EIA) data as showing that for all different types of storms or “disturbances”, hurricanes/tropical storms, summer storms, and winter storms (ice/snow) make up “more than 97.8 percent of all the events recorded” (p. 14).  All events included earthquake, flooding, heat storm, hurricane/tropical storm, summer storm (lightning/high winds), wildfire, and winter storms (ice/snow).  The EIA deducted that storms that produce strong winds are the “major cause of warm weather and grid failures” (p. 15).  The data further showed that “hurricanes/tropical storms and summer storms cause 80 percent of all major outages and that snow and ice accumulation are the major cause of system outages during the winter” (pp. 15-16).  Given this, one might conclude that UG systems would be less susceptible to damage.  But, in reality, most underground systems are generally fed electricity by overhead facilities.  So, an event that causes overhead line power disruption will inevitably cause disruption to the underground system as well. 

The EEI also studied major storm data for a period of nine years to determine trends and impacts these events had on the electric industry.  The data was somewhat inconclusive in that storm patterns were increasing, but average outage time per customer declined in some instances.  This may have been due to improvements in restoration response time due to increased use of mutual assistance from other electric utility companies.  Additionally, UG facilities seemed to have had a slightly better performance than OH facilities in some instances, while a much better performance in others.  UG facilities were particularly susceptible to poor performance in areas where flooding occurs.   

In order to get an understanding of how to determine the decision to go underground, one needs to understand the benefits and challenges associated with these decisions.  The following lists of benefits and challenges is provided directly from the 2012 EEI poll responses (Hall, 2013), and is a comprehensive listing of all aspects surrounding these.  Each of these listed may or may not apply to one specific area or company, but instead represent the poll feedback from their association members across the US.  Benefits include improved reliability in some instances, aesthetics, and others as listed.  Challenges include costs, operation and maintenance, failure issues, and others as listed.   

Benefits of Undergrounding

Reliability

Aesthetics

Other

Challenges of Undergrounding

Costs

Operation and Maintenance

Failure Issues

Other

Costs of Undergrounding

The EEI also collected data in it’s 2012 survey on cost per mile of UG vs. OH construction.  The following tables represent their findings. 

Table Legend:

Urban:  150+ customers per square mile

Suburban:  51 to 149 customers per square mile

Rural:  50 or fewer customers per square mile

Table 6.1 Cost per Mile: New Construction Transmission

 

Overhead

Underground

Urban

Suburban

Rural

Urban

Suburban

Rural

Minimum

$377,000

$232,000

$174,000

$3,500,000

$2,300,000

$1,400,000

Maximum

$11,000,000

$4,500,000

$6,500,000

$30,000,000

$30,000,000

$27,000,000

For rural electric cooperatives, the survey data suggested that new construction transmission costs at the Minimum level could range 8 times the amount of overhead costs to construct underground facilities while at a Maximum level could range 4 times the amount.

Table 6.2 Cost per Mile: New Construction Distribution

 

Overhead

Underground

Urban

Suburban

Rural

Urban

Suburban

Rural

Minimum

$126,900

$110,800

$86,700

$1,141,300

$528,000

$297,200

Maximum

$1,000,000

$908,000

$903,000

$4,500,000

$2,300,000

$1,840,000

For rural electric cooperatives, the survey data suggested that new construction distribution costs at the Minimum level could range 3.5 times the amount of overhead costs to construct underground facilities while at a Maximum level could range 2 times the amount.

Table 6.3 Cost per Mile: Converting Overhead to Underground Transmission

 

Urban

Suburban

Rural

Minimum

$536,760

$1,100,000

$1,100,000

Maximum

$12,000,000

$11,000,000

$6,000,000

For rural electric cooperatives, the survey data suggested that the cost of converting overhead to underground transmission facilities could range from a Minimum of $1,100,000 per mile to a Maximum of $6,000,000 per mile.

Table 6.4 Cost per Mile: Converting Overhead to Underground Distribution

 

Urban

Suburban

Rural

Minimum

$1,000,000

$313,600

$158,100

Maximum

$5,000,000

$2,420,000

$1,960,000

For rural electric cooperatives, the survey data suggested that the cost of converting overhead to underground distribution facilities could range from a Minimum of $158,100 per mile to a Maximum of $1,960,000 per mile. (Hall, pp. 30-31)